From April 2025 to February 2026, our team was on site delivering key electrical works for INTEC Energy Solutions at the Twin Rivers Solar Farm in Kaitaia, Northland.

Located in a remote area, this 31MW utility-scale solar development required detailed planning, strong logistics coordination, and a committed delivery team. Two crews operated on rotation throughout the project, staying out of town and working weekends to maintain programme momentum.

The Twin Rivers Solar Farm consists of:

  • 55,832 ground-mounted frame PV modules

  • 120 string combiner boxes

  • 6 GE inverters

  • 31MW generation capacity

It will be capable of generating enough renewable energy to power more than 6,000 households annually - or the equivalent of charging approximately 25,000 electric vehicles per year.


Our scope of works included:

  • Installation of all DC cabling and terminations
  • Installation of all string DC cabling and terminations
  • Installation of all HV cable installation
  • Installation of underground fibre optics
  • Installation of main earth ring around transformer
  • Installation of all combiner boxes and terminations
  • Installation of all inverters and terminations
  • Connections of all PV modules
  • Earthing and bonding
  • Installation of weather, meteorological, and hydrologic stations
  • Testing, commissioning, QA, and labelling of all works

PROJECT

Solar Farm

LOCATION

Northland

YEAR

2025-2026